This project involved the restoration of a channel downstream of a pond to reduce erosion potential. As the general contractor, Iron Woman’s work included 4,000 cubic yards of CIP earthwork; the removal of multiple structures (36-inch RCP, 60-inch CMP, a concrete trail, concrete weir); 110 square yards of sheetpile; 109 linear feet of 8-foot by 5-foot concrete box culvert; 1,000 cubic yards of varying riprap; 600 linear feet of 24-inch instream boulder vains; 280 square yards of 24-inch grouted boulders; 150 linear foot boulder retaining wall; 280 linear feet of rootwads; 45 linear feet of 36-inch RCP and FES; 30 linear feet of 12-inch steel casing pipe; and associated plantings.



Client
City of Colorado Springs
Owner

City of Colorado Springs